It was a busy year refurbishing Sunny Bank Mills for offices in 2016! January-Feb

  • Reconfigure two units in the Mending Rooms
  • Demolish the old garage

February-May

  • Build overflow car park
  • Create new store in Twisting Gallery.
  • Create 2 new units in the Old Combing
  • Fit-out new unit in 1912 Mill

June-July

  • Refurbish new unit in Mending Rooms

September-December

  • Extensively refurbish Ground Floor of Red Lane Mill
  • Replace roof of Twisting Gallery
  • Fully refurbish unit 1 Old Engine Room